Pine Grove Energy Storage
150 MW storage in Lewis, NY · In queue since September 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Pine Grove Energy Storage project is a proposed 150 MW battery storage project located in Lewis County, New York. Developed by BGTF US Development Holdings LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry C24-126, with a queue entry date of September 5, 2024. The proposed commercial operation date is December 1, 2028.
The project consists of 150 MW of battery storage capacity. It is interconnected to the grid at the Austin Road 345 kV point of interconnection. The project is currently listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Lewis
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BGTF US Development Holdings LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Austin Road 345 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pine Grove Energy Storage