Crescent Energy Storage
75 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD December 2028
75 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Crescent Energy Storage is a proposed 75 MW battery storage project located in Chautauqua County, New York. The project, developed by BGTF US Development Holdings LLC, is interconnected to the NYISO grid under queue ID NYISO-C24-127. It entered the interconnection queue on September 5, 2024, with a proposed commercial operation date of December 1, 2028.
The Crescent Energy Storage project is currently active in the NYISO interconnection queue. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BGTF US Development Holdings LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Moons Road to Falconer 115 kV Line 175
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Crescent Energy Storage