Buffalo Road Energy Storage
100 MW storage in Niagara, NY · In queue since September 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Buffalo Road Energy Storage is a proposed 100 MW battery storage project located in Niagara County, New York. The project, being developed by MN8 Energy Development Company LLC, is interconnected within the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-129. The project entered the queue on September 5, 2024, with a proposed commercial operation date of December 1, 2028.
The proposed project has appeared in recent news coverage related to industry and development.
Generated from interconnection queue and public data sources
State
NY
County
Niagara
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
MN8 Energy Development Company LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Dupont to Packard 115 kV Line #184
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Buffalo Road Energy Storage