Elevate Bethlehem
120 MW storage in Albany, NY · In queue since September 2024 · Proposed COD June 2027
120 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
Elevate Bethlehem is a proposed 120 MW battery storage project located in Albany County, New York. Developed by Elevate Bethlehem, LLC, the project entered the NYISO interconnection queue on September 5, 2024, under queue ID NYISO-C24-130. The proposed commercial operation date is June 1, 2027. The point of interconnection is the Albany Steam 115 kV Substation.
The project consists of 120 MW of battery storage. It is currently listed as active in the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Albany
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Elevate Bethlehem, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Albany Steam 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BETHLHEM_115KV_TB1
- POI Substation
- Albany Steam Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.