Cross County Energy Storage
130 MW storage in Westchester, NY · In queue since September 2024 · Proposed COD June 2028
130 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Cross County Energy Storage is a proposed 130 MW battery storage project located in Westchester County, New York. The project, developed by HW Power, LLC, is interconnected to the ConEd utility network. It entered the NYISO interconnection queue on September 6, 2024, under queue ID NYISO-C24-132, with a proposed commercial operation date of June 1, 2028.
The project is currently listed as active in the NYISO queue. It consists of 130 MW of battery storage capacity. The point of interconnection is the Eastview to Buchanan 345 kV line. The project has been mentioned in recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Westchester
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
HW Power, LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Eastview to Buchanan, 345 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE I
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Cross County Energy Storage