Sandlot IFB
50 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD October 2029
50 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
Sandlot IFB is a proposed 50 MW battery storage project located in Suffolk County, New York. Developed by Sandlot Energy LLC, the project is interconnected to the Long Island Power Authority (LIPA) grid. It entered the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-C24-154 on September 11, 2024, with a proposed commercial operation date of October 1, 2029.
The project is currently listed as active in the NYISO interconnection queue. The point of interconnection (POI) is the Deposit - Indian Head 69 kV Line.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Sandlot Energy LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Deposit - Indian Head 69 kV Line
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.