Cruiser BESS
100 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD March 2028
100 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Cruiser BESS project is a proposed 100 MW battery storage project located in Suffolk County, New York. Developed by Viridity Energy Solutions, the project is interconnected to the Long Island Power Authority (LIPA) via the Pulaski 69kV point of interconnection. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-159, with a queue entry date of September 12, 2024, and a proposed commercial operation date of March 1, 2028.
The proposed project consists of 100 MW of battery storage capacity. It is in the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Viridity Energy Solutions
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Pulaski 69kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- HIGH
- POI Substation
- Pulaski Substation