Zenith BESS
165 MW storage in Onondaga, NY · In queue since September 2024 · Proposed COD October 2029
165 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
Zenith Power LLC is proposing the Zenith BESS project, a 165 MW battery storage development in Onondaga County, New York. The project is located within the NYISO region and interconnected to the Geres Lock-Tilden Line 16 115kV.
The Zenith BESS project entered the NYISO interconnection queue as project number NYISO-C24-170 on September 17, 2024. Its proposed commercial operation date is October 1, 2029. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
NY
County
Onondaga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Zenith Power LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Geres Lock-Tilden Line 16 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Zenith BESS