North Chelsea (Fieldstone Power Station) (NYISO-C24-171) — Project Summary

Queue ID
NYISO-C24-171
Capacity
150 MW
Technology
Battery
Status
active
Location
Dutchess, NY
Region
NYISO
Developer
Fieldstone Power Station LLC
IA Status

North Chelsea (Fieldstone Power Station)

NYISO-C24-171BetaActiveBatteryNYISOLBNL

150 MW storage in Dutchess, NY · In queue since September 2024 · Proposed COD May 2028

150 MW

Capacity

1

Components

Battery

1y 8m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

3y 8m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

About

The North Chelsea (Fieldstone Power Station) is a proposed 150 MW battery storage project located in Dutchess County, New York. Developed by Fieldstone Power Station LLC, the project consists of a 150 MW battery component. It is listed in the NYISO interconnection queue as entry NYISO-C24-171, with a queue entry date of September 17, 2024, and a proposed commercial operation date of May 1, 2028. The point of interconnection is the North Chelsea 115 kV Substation.

The proposed project is currently listed as active in the NYISO interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Dutchess

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Fieldstone Power Station LLC

Utility

CHGE

Entity

NYISO

Service Type

Point of Interconnection

North Chelsea 115 kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE G
Hub Confidence
HIGH
Nearest Node (Estimated)
NCHELSEA_115KV_TR2
POI Substation
North Chelsea Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about North Chelsea (Fieldstone Power Station)