BRESH HYBRID
59.2 MW hybrid in Ulster, NY · In queue since September 2024 · Proposed COD December 2027
59.2 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRESH HYBRID project is a proposed solar and battery energy storage development with a total capacity of 59.2 MW. Located in Ulster County, New York, the project is being developed by Blue Stone Renewable XVI. It consists of 59.2 MW of solar generation co-located with battery storage.
The project is currently active in the NYISO interconnection queue as entry NYISO-C24-172, with a queue entry date of September 17, 2024. The proposed commercial operation date is December 1, 2027. The point of interconnection is the BOULEVARD 69 kV SUBSTATION, and Central Hudson Gas & Electric (CHGE) is the utility.
Generated from interconnection queue and public data sources
State
NY
County
Ulster
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Blue Stone Renewable XVI
Utility
CHGE
Entity
NYISO
Service Type
—
Point of Interconnection
BOULEVARD 69 kV SUBSTATION
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- POI Substation
- Sunset Boulevard Substation