Tabletop Solar
80 MW generation in Montgomery, NY · In queue since September 2024 · Proposed COD December 2027
80 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Tabletop Solar is a proposed 80 MW solar generation project located in Montgomery County, New York. The project, developed by Tabletop Solar NY LLC, is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-184, with a queue entry date of September 18, 2024. The proposed commercial operation date is December 1, 2027.
This development is linked to the existing SunEast Tabletop Solar Project operating plant (EIA ID 63867). The point of interconnection is the Clinton Tap off the Inghams-Meco-Marshviille Line 15 115kV.
Generated from interconnection queue and public data sources
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Tabletop Solar NY LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Clinton Tap off the Inghams-Meco-Marshviille Line 15 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone E
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tabletop Solar