THOR SOLAR
36.6 MW generation in Rensselaer, NY · In queue since September 2024 · Proposed COD August 2028
36.6 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The THOR SOLAR project is a proposed 36.6 MW solar generation project located in Rensselaer County, New York. Developed by Blue Stone Renewable III, the project is currently active in the NYISO interconnection queue as entry NYISO-C24-186, with a queue entry date of September 18, 2024. The proposed commercial operation date is August 1, 2028.
The project will interconnect to the Transco utility at the Schodack - Falls Park 115kV point of interconnection. It has appeared in recent news coverage regarding renewable energy development in New York.
Generated from interconnection queue and public data sources
State
NY
County
Rensselaer
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Blue Stone Renewable III
Utility
Transco
Entity
NYISO
Service Type
—
Point of Interconnection
Schodack - Falls Park 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about THOR SOLAR