Wheelhouse Solar Energy Center
350 MW hybrid in Herkimer, NY · In queue since September 2024 · Proposed COD December 2029
350 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Wheelhouse Solar Energy Center is a proposed 350 MW hybrid solar and battery project located in Herkimer County, New York. Developed by Wheelhouse Solar Energy Center, LLC, the project consists of 350 MW of solar generation. It is interconnected to the NYISO grid under queue ID NYISO-C24-188, with a queue entry date of September 18, 2024, and a proposed commercial operation date of December 1, 2029.
The proposed project is currently in the active stage of the interconnection queue. The point of interconnection is the Edic 345 kV (137200) to Princetown 345 kV (148965) southern circuit #352. The utility is NYPA, and the entity is NYISO. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Herkimer
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Wheelhouse Solar Energy Center, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Edic 345 kV (137200) to Princetown 345 kV (148965) southern circuit #352
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Wheelhouse Solar Energy Center