Brusselville Solar Energy Center
170 MW hybrid in Genesee, NY · In queue since September 2024 · Proposed COD December 2029
170 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Brusselville Solar Energy Center is a proposed 170 MW hybrid solar and battery project located in Genesee County, New York. Developed by Brusselville Solar, LLC, the project consists of 170 MW of solar capacity. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-202, with a queue entry date of September 19, 2024, and a proposed commercial operation date of December 1, 2029.
The project intends to interconnect to the Dysinger-New Rochester 345kV Line (DH2) and is under the purview of utility NYPA.
Generated from interconnection queue and public data sources
State
NY
County
Genesee
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Brusselville Solar, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Dysinger-New Rochester 345kV Line (DH2)
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Brusselville Solar Energy Center