Mill Run BESS (NYISO-C24-203) — Project Summary

Queue ID
NYISO-C24-203
Capacity
260 MW
Technology
Battery
Status
active
Location
Onondaga, NY
Region
NYISO
Developer
Renew Development HoldCo LLC
IA Status

Mill Run BESS

NYISO-C24-203BetaActiveBatteryNYISOLBNL

260 MW storage in Onondaga, NY · In queue since September 2024 · Proposed COD September 2028

260 MW

Capacity

1

Components

Battery

1y 8m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4 years

Pre-Study0%
Queue EntrySep 19, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

Mill Run BESS is a proposed 260 MW battery storage project located in Onondaga County, New York. Developed by Renew Development HoldCo LLC, the project consists of 260 MW of battery capacity. It is currently active in the NYISO interconnection queue under queue ID NYISO-C24-203, with an interconnection queue entry date of September 19, 2024, and a proposed commercial operation date of September 1, 2028.

The project is interconnected to the Elbridge - Geres Lock 115kV 18 & 19 lines. Recent news coverage indicates activity related to regulatory and industry developments surrounding the project.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Onondaga

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Renew Development HoldCo LLC

Utility

NM-NG

Entity

NYISO

Service Type

Point of Interconnection

Elbridge - Geres Lock 115kV 18 & 19 lines

Data Source

LBNL

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE C
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Mill Run BESS