Independence BESS
200 MW storage in Oswego, NY · In queue since September 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Independence BESS is a proposed 200 MW battery storage project located in Oswego County, New York. Developed by Independence BESS LLC, the project is interconnected to the NYISO grid at the Independence 345 KV point of interconnection. It entered the NYISO interconnection queue as project number C24-208 on September 19, 2024, with a proposed commercial operation date of June 1, 2028.
The Independence BESS project is currently listed as active in the NYISO interconnection queue. Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Independence BESS LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Independence 345 KV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Independence Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Independence BESS