Mulberry Energy Storage
130 MW storage in Saratoga, NY · In queue since September 2024 · Proposed COD June 2029
130 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Mulberry Energy Storage is a proposed 130 MW battery storage project located in Saratoga County, New York. The project, being developed by Mulberry Energy Storage 1, LLC, is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-214, with a queue entry date of September 20, 2024. The current proposed commercial operation date is June 1, 2029.
The project consists of 130 MW of battery storage capacity. Mulberry Energy Storage has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Saratoga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Mulberry Energy Storage 1, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Luther Forest-Eastover Rd 115kV Line 308
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Mulberry Energy Storage