Snowy Knoll Wind Project
350 MW hybrid in Oneida, NY · In queue since September 2024 · Proposed COD June 2030
350 MW
Capacity
1
Components
Wind
1y 8m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Snowy Knoll Wind Project is a proposed 350 MW hybrid wind and battery energy storage project located in Oneida County, New York. Developed by Snowy Knoll Wind Project, LLC, the project consists of 350 MW of wind generation capacity. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-221-003, with a queue entry date of September 20, 2024, and a proposed commercial operation date of June 1, 2030.
The project intends to interconnect to the NYPA utility grid at the Edic - Fraser 345kV point of interconnection. The Snowy Knoll Wind Project has appeared in recent news coverage regarding renewable energy development in New York State.
Generated from interconnection queue and public data sources
State
NY
County
Oneida
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Snowy Knoll Wind Project, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Edic - Fraser 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Snowy Knoll Wind Project