Queen Energy Center
140 MW storage in Tompkins, NY · In queue since September 2024 · Proposed COD November 2029
140 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
The Queen Energy Center is a proposed 140 MW battery storage project located in Tompkins County, New York. Developed by Mission Clean Energy Devco, LLC, the project is interconnected to the NYSEG utility via the Etna - Milliken 115 kV line. It is listed in the NYISO interconnection queue as entry C24-223, with a queue entry date of September 20, 2024, and a proposed commercial operation date of November 1, 2029.
The Queen Energy Center development has been the subject of recent news coverage, with eight articles published across industry, grid, and regulatory categories. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Tompkins
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Mission Clean Energy Devco, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Etna - Milliken 115 kV line
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Queen Energy Center