South Dow (Lucy's Energy Reserve)
175 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD May 2028
175 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The South Dow (Lucy's Energy Reserve) project is a proposed 175 MW battery storage project located in Chautauqua County, New York. Developed by Lucy?s Energy Reserve LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-226. The project entered the queue on September 20, 2024, with a proposed commercial operation date of May 1, 2028.
The project, which consists of 175 MW of battery storage, is planned for interconnection at the Falconer 115kV Substation. Recent news coverage indicates ongoing development activity.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Lucy?s Energy Reserve LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Falconer 115kV Substation
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- HIGH
- POI Substation
- Falconer Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about South Dow (Lucy's Energy Reserve)