South Dow 2 (Lucy's Energy Reserve 2)
125 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD May 2028
125 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The South Dow 2 (Lucy's Energy Reserve 2) project is a proposed 125 MW battery storage project located in Chautauqua County, New York. The project, developed by Lucy's Energy Reserve LLC, is currently active in the NYISO interconnection queue as entry NYISO-C24-227, with a queue entry date of September 20, 2024. The proposed commercial operation date is May 1, 2028.
The project will interconnect at the Falconer-South Dow Line 154 115kV. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Lucy?s Energy Reserve LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Falconer-South Dow Line 154 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.