30 MW generation in Washington, NY · In queue since September 2024 · Proposed COD December 2027
30 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Champlain Solar Uprate is a proposed 30 MW solar generation project located in Washington County, New York. Developed by RWE Clean Energy Development, LLC, the project consists of 30 MW of solar photovoltaic capacity. It is listed in the NYISO interconnection queue as entry NYISO-C24-235, with a queue entry date of September 22, 2024, and a proposed commercial operation date of December 1, 2027.
The project is currently listed as active in the interconnection queue. The point of interconnection is the Mohican - Whitehall 115 kV Line 13. The Champlain Solar Uprate has appeared in recent news coverage regarding renewable energy projects in New York.
Generated from interconnection queue and public data sources
State
NY
County
Washington
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Clean Energy Development, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Mohican - Whitehall 115 kV Line 13
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Champlain Solar Uprate