Champlain Solar
90 MW generation in Washington, NY · In queue since September 2024 · Proposed COD December 2027
90 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Champlain Solar is a proposed 90 MW solar generation project located in Washington County, New York. The project, being developed by RWE Clean Energy Development, LLC, is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-236. The project entered the queue on September 22, 2024, with a proposed commercial operation date of December 1, 2027.
The Champlain Solar project is currently listed as active in the interconnection queue. Recent news coverage indicates interest in the project related to grid and regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Washington
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Clean Energy Development, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Mohican - Whitehall 115 kV Line 13
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Champlain Solar