PA-Hockenberry LLC
400 MW generation in Jefferson, PA · In queue since September 2024 · Proposed COD November 2028
400 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
PA-Hockenberry LLC is proposing a 400 MW solar generation project in Jefferson County, Pennsylvania. The project, developed by PA-Hockenberry LLC, is located within the New York Independent System Operator (NYISO) region. Designated as queue ID NYISO-C24-245, the project entered the NYISO interconnection queue on September 23, 2024, with a proposed commercial operation date of November 1, 2028.
The point of interconnection for the proposed project is a tap on the Homer City to Pierce Brook 345kV line. The project is currently listed as "active" in the interconnection queue. The interconnecting utility is New York State Electric and Gas (NYSEG).
Generated from interconnection queue and public data sources
State
PA
County
Jefferson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
PA-Hockenberry LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Tap on Homer City to Pierce Brook 345kV line
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.