Block Perch solar
85 MW generation in Chautauqua, NY · In queue since September 2024 · Proposed COD November 2029
85 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
The Block Perch solar project is a proposed 85 MW solar generation project located in Chautauqua County, New York. Developed by ACE DevCo NC LLC, the project consists of 85 MW of solar photovoltaic generation. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-C24-246, with a queue entry date of September 23, 2024.
The proposed commercial operation date for the Block Perch solar project is November 1, 2029. The point of interconnection is the Moon Road-Falconer Line 175 115V. The project is listed in the interconnection queue of the NYISO.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ACE DevCo NC LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Moon Road-Falconer Line 175 115V
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Block Perch solar