Jerry Smith Energy Storage
34.9 MW storage in Tompkins, NY · In queue since September 2024 · Proposed COD January 2029
34.9 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-01
The Jerry Smith Energy Storage project is a proposed 34.9 MW battery storage project located in Tompkins County, New York. The developer is Nexamp Solar LLC, and the project is interconnected with NYSEG. It is listed in the NYISO interconnection queue as entry NYISO-C24-247, with a queue entry date of September 23, 2024, and a proposed commercial operation date of January 1, 2029.
The project is currently listed as "active" in the interconnection queue. The point of interconnection is the Milliken to Ludlowville 34.5kV Line#522, specifically on the N.Lansing-Ludlowville 2.11mi section.
Generated from interconnection queue and public data sources
State
NY
County
Tompkins
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Nexamp Solar LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Milliken to Ludlowville 34.5kV Line#522 -on N.Lansing-Ludlowville 2.11mi section
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jerry Smith Energy Storage