Dove Energy Storage
79.9 MW storage in Montgomery, NY · In queue since September 2024 · Proposed COD July 2027
79.9 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
Dove Energy Storage is a proposed 79.9 MW battery storage project located in Montgomery County, New York. The project, developed by Dove Energy Storage, is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-248. The queue entry date is September 23, 2024, with a proposed commercial operation date of July 1, 2027.
The point of interconnection is the St. Johnsville - Marshville 115 kV line, identified as line #11, which is undergoing a CLCPA rebuild. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Dove Energy Storage
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
St. Johnsville - Marshville, Line id #11 (CLCPA rebuild), 115 kV,
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dove Energy Storage