Troy Heights Energy Storage
40 MW storage in Tompkins, NY · In queue since September 2024 · Proposed COD December 2028
40 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Troy Heights Energy Storage project is a proposed 40 MW battery storage project located in Tompkins County, New York. Developed by Nexamp Solar LLC, the project is interconnected to the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-253. The project entered the queue on September 23, 2024, and has a proposed commercial operation date of December 1, 2028.
The project will interconnect to the Coddington Substation at 34.5 kV. The Troy Heights Energy Storage project is currently listed as active in the NYISO interconnection queue. The project has appeared in recent news coverage regarding energy storage development in New York.
Generated from interconnection queue and public data sources
State
NY
County
Tompkins
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Nexamp Solar LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Coddington Substation 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Troy Heights Energy Storage