Christmas Tree
25 MW hybrid in Schuyler, NY · In queue since September 2024 · Proposed COD December 2027
25 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Christmas Tree project is a proposed 25 MW hybrid solar and battery energy storage development project located in Schuyler County, New York. The project, developed by Nexamp Solar LLC, consists of 25 MW of solar generation. It is interconnected to the New York State Electric and Gas (NYSEG) system at the Cayuta to Ridge Road 34.5 kV Line# 501 point of interconnection.
The project is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-259, with a queue entry date of September 23, 2024, and a proposed commercial operation date of December 1, 2027. The project currently has an active status in the queue and has been featured in recent industry news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Schuyler
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Nexamp Solar LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Cayuta to Ridge Road 34.5 kV Line# 501
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM