West Laurens
350 MW generation in Otsego, NY · In queue since September 2024 · Proposed COD December 2029
350 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The West Laurens project is a proposed 350 MW solar generation project located in Otsego County, New York. Developed by ACE DevCo NC, LLC, the project is interconnected to the NYISO grid at the Marcy to Coopers Corner - 345 kV point of interconnection. It is listed in the NYISO interconnection queue as entry C24-260, with a queue entry date of September 23, 2024, and a proposed commercial operation date of December 1, 2029.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
NY
County
Otsego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ACE DevCo NC, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Marcy to Coopers Corner - 345 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about West Laurens