EI Steinway 1
1,300 MW generation in Queens, NY · In queue since September 2024 · Proposed COD February 2034
1,300 MW
Capacity
1
Components
Offshore Wind
1y 8m
In Queue
—
IA Status
COD target: 2034
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2034-02-01
The EI Steinway 1 project is a proposed 1300 MW offshore wind generation project located in Queens County, New York. Developed by Beacon Wind LLC, the project is interconnected to the ConEd utility and participates in the NYISO interconnection queue under queue ID NYISO-C24-261. The project entered the queue on September 23, 2024, with a proposed commercial operation date of February 1, 2034.
The point of interconnection for EI Steinway 1 is the Mott Haven to Rainey 345kV line tap. The project is currently listed as active in the interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Queens
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Beacon Wind LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Mott Haven to Rainey 345kV line tap
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about EI Steinway 1