Berry Farm Storage
120 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD June 2029
120 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Berry Farm Storage is a proposed 120 MW battery storage project located in Chautauqua County, New York. Developed by Berry Farm Storage 1, LLC, the project entered the NYISO interconnection queue on September 23, 2024, under queue ID NYISO-C24-264. The proposed commercial operation date is June 1, 2029.
The project is interconnected to the L160 115 kV line between Dunkirk and Falconer. Berry Farm Storage has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Berry Farm Storage 1, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
L160 115 kV line (Dunkirk and Falconer)
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Berry Farm Storage