Sullivan-Woodbourne Solar Project
100 MW generation in Sullivan, NY · In queue since September 2024 · Proposed COD November 2028
100 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The proposed Sullivan-Woodbourne Solar Project is a 100 MW solar generation project located in Sullivan County, New York. Developed by the NY Power Authority, the project is interconnected to the NYSEG utility via the Mountaindale - Woodbourne 115 kV line. It is listed in the NYISO interconnection queue as entry C24-278, with a queue entry date of September 24, 2024, and a proposed commercial operation date of November 1, 2028.
The project consists of 100 MW of solar photovoltaic generation capacity. The Sullivan-Woodbourne Solar Project is currently listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Sullivan
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
NY Power Authority
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Mountaindale - Woodbourne 115 kV line
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sullivan-Woodbourne Solar Project