Genovia Storage
300 MW storage in Genesee, NY · In queue since September 2024 · Proposed COD August 2028
300 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The Genovia Storage project is a proposed 300 MW battery storage project located in Genesee County, New York. Developed by Genovia Storage LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-289, with a queue entry date of September 27, 2024. The proposed commercial operation date is August 1, 2028, and the point of interconnection is the 345 kV Line 1 QP580_POI2 Substation to Q721_POI Substation.
The project is currently listed as active in the interconnection queue. It has appeared in recent news coverage related to deals.
Generated from interconnection queue and public data sources
State
NY
County
Genesee
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Genovia Storage LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
345 kV Line 1 QP580_POI2 Substation to Q721_POI Substation
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.