Oswego Clean Energy
24.9 MW generation in Oswego, NY · In queue since September 2024 · Proposed COD December 2026
24.9 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The Oswego Clean Energy project is a proposed 24.9 MW solar generation facility located in Oswego County, New York. The project, developed by Oswego Clean Energy Holdings, is interconnected to the NYISO grid under queue ID NYISO-C24-293. Its point of interconnection is the Oswego 115 kV Substation.
The project entered the NYISO interconnection queue on September 27, 2024, and has a proposed commercial operation date of December 1, 2026. The project is currently listed as active in the interconnection queue. The utility associated with the project is NM-NG.
Generated from interconnection queue and public data sources
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Oswego Clean Energy Holdings
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Oswego 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Oswego Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Oswego Clean Energy