Birch-Whistler
100 MW generation in Delaware, NY · In queue since September 2024 · Proposed COD December 2030
100 MW
Capacity
1
Components
Wind
1y 8m
In Queue
—
IA Status
COD target: 2030
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-01
The Birch-Whistler project is a proposed 100 MW wind generation facility in Delaware County, New York. Developed by Birch Whistler, LLC, the project is interconnected to the NYISO grid at the Line Tap Edic to Fraser Line, 345kV. It entered the NYISO interconnection queue as queue ID NYISO-C24-294 on September 27, 2024, and has a proposed commercial operation date of December 1, 2030.
The project is currently listed as active in the interconnection queue. The designated utility for the project is the New York Power Authority (NYPA). The project has appeared in recent news coverage regarding renewable energy development in New York.
Generated from interconnection queue and public data sources
State
NY
County
Delaware
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Birch Whistler, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Line Tap Edic to Fraser Line, 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Birch-Whistler