Medina Solar
100 MW generation in Orleans, NY · In queue since September 2024 · Proposed COD October 2029
100 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
The Medina Solar project is a proposed 100 MW solar generation project located in Orleans County, New York. Developed by ACE DevCo NC LLC, the project is currently active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-C24-296. The project's point of interconnection is planned for the Brunner to Sour Springs 115 kV Line 118.
The project entered the NYISO queue on September 27, 2024, with a proposed commercial operation date of October 1, 2029. The project consists of 100 MW of solar photovoltaic generation capacity. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Orleans
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ACE DevCo NC LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Connection on Brunner to Sour Springs 115 kV Line 118
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Medina Solar