Deer River
100 MW generation in Lewis, NY · In queue since September 2024 · Proposed COD December 2029
100 MW
Capacity
1
Components
Wind
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Deer River project is a proposed 100 MW wind generation facility in Lewis County, New York. Developed by Deer River Wind, LLC, the project is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-297, with a queue entry date of September 27, 2024. The proposed commercial operation date is December 1, 2029.
The point of interconnection for the Deer River project is the Black River-Lighthouse Hill Line 5 115kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Lewis
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Deer River Wind, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Black River-Lighthouse Hill Line 5 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Deer River