Black Cherry Wind 2
150 MW generation in Cameron, PA · In queue since September 2024 · Proposed COD December 2029
150 MW
Capacity
1
Components
Wind
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Black Cherry Wind 2 is a proposed 150 MW wind generation project located in Cameron County, Pennsylvania. The project, developed by Black Cherry Wind Power, LLC, is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-299. The project's queue entry date is September 29, 2024, with a proposed commercial operation date of December 1, 2029.
The project intends to interconnect to the NYSEG utility grid at the Homer City - Piercebrook 345kV point of interconnection. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
PA
County
Cameron
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Black Cherry Wind Power, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Homer City - Piercebrook 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Black Cherry Wind 2