Moonlight Flats Solar
250 MW generation in Clearfield, PA · In queue since September 2024 · Proposed COD March 2029
250 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-01
Moonlight Flats Solar is a proposed 250 MW solar generation project located in Clearfield County, Pennsylvania. The developer is Moonlight Flats Solar Power, LLC. The project is interconnected to the NYISO grid under queue ID NYISO-C24-301, with a queue entry date of September 30, 2024, and a proposed commercial operation date of March 1, 2029. The point of interconnection is the Homer City 345 kV to Mainesburg 345 kV L47 line, and the interconnecting utility is NYSEG.
The proposed project is linked to the existing Moonlight Flats Solar Power 1 operating plant (EIA plant ID 67950). The project has appeared in recent news coverage related to grid issues.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Moonlight Flats Solar Power, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Homer City 345 kV to Mainesburg 345 kV L47
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone A
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Moonlight Flats Solar