NY Oswego 200 Erie St Storage
142 MW storage in Oswego, NY · In queue since September 2024 · Proposed COD April 2028
142 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The NY Oswego 200 Erie St Storage project is a proposed 142 MW battery storage project located in Oswego County, New York. Developed by McMullen Pond LLC, the project entered the NYISO interconnection queue on September 30, 2024, under queue ID NYISO-C24-302. The proposed commercial operation date is April 1, 2028.
The project is interconnected to the Oswego - S Oswego 115kV circuit 3. As of the current data, the project has an active status in the NYISO queue and has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
McMullen Pond LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Oswego - S Oswego 115kV circuit 3
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.