NY Chateaugay 0 Willis Rd Storage
150 MW storage in Franklin, NY · In queue since October 2024 · Proposed COD April 2028
150 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The NY Chateaugay 0 Willis Rd Storage project is a proposed 150 MW battery storage project located in Franklin County, New York. The developer is Chateauguay River, LLC, and the interconnecting utility is the New York Power Authority (NYPA). The project is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-304-004, with a queue entry date of October 1, 2024, and a proposed commercial operation date of April 1, 2028.
The project is planned to interconnect at the Willis 230kV substation. The project has appeared in recent news coverage related to grid development.
Generated from interconnection queue and public data sources
State
NY
County
Franklin
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Chateauguay River, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Willis 230kV substation
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- HIGH
- POI Substation
- Willis Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.