Lock 26 BESS
50 MW storage in Wayne, NY · In queue since October 2024 · Proposed COD December 2028
50 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Lock 26 BESS project is a proposed 50 MW battery storage project located in Wayne County, New York. Developed by Oriden, the project is interconnected to the RG&E utility network. It is listed in the NYISO interconnection queue as entry NYISO-C24-306, with a queue entry date of October 1, 2024, and a proposed commercial operation date of December 1, 2028.
The development project consists of a 50 MW battery energy storage system. The Lock 26 BESS project has been featured in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
NY
County
Wayne
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Oriden
Utility
RG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Clyde 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- HIGH
- POI Substation
- Clyde Substation