Lincoln ESC
100 MW storage in Suffolk, NY · In queue since October 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Lincoln ESC project is a proposed 100 MW battery storage project located in Suffolk County, New York. Developed by Fresh Air Energy II, LLC, it is interconnected within the New York Independent System Operator (NYISO) queue as project number NYISO-C24-310. The project entered the queue on October 2, 2024, with a proposed commercial operation date of December 1, 2028.
The Lincoln ESC project will interconnect to the LIPA utility grid at the Holbrook - Bohemia Ckt#1, 69kV point of interconnection. As of the latest data, the project's interconnection agreement status is active within the NYISO queue. The development has also appeared in recent news coverage regarding energy storage projects in the New York region.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Fresh Air Energy II, LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Holbrook - Bohemia Ckt#1, 69kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.