St. Regis
58.5 MW hybrid in St. Lawrence, NY · In queue since October 2024 · Proposed COD May 2028
58.5 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The St. Regis project is a proposed 58.5 MW hybrid solar and battery energy storage development in St. Lawrence County, New York. The project, developed by BW Solar Holding Inc., consists of a 58.5 MW solar component. It is located in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-C24-312, with an entry date of October 2, 2024, and a proposed commercial operation date of May 1, 2028.
The point of interconnection for the St. Regis project is the Dennison-Colton #5 115kV Line. The project is currently listed as active in the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
St. Lawrence
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BW Solar Holding Inc.
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Dennison-Colton #5 115kV Line.
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about St. Regis