DOVER NY BESS
1,000 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD September 2028
1,000 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
The proposed DOVER NY BESS project is a 1000 MW battery storage development in Dutchess County, New York. Developed by DOVER PLAINS ENERGY PROPERTIES LLC, the project is located within the NYISO region and will interconnect with ConEd at the Pleasant Valley-Cricket Valley 345kV point of interconnection.
The project entered the NYISO interconnection queue as queue ID NYISO-C24-316 on October 3, 2024, and has a proposed commercial operation date of September 1, 2028. The project's interconnection status is currently active.
Generated from interconnection queue and public data sources
State
NY
County
Dutchess
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
DOVER PLAINS ENERGY PROPERTIES LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Pleasant Valley-Cricket Valley 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about DOVER NY BESS