Rolling Upland Wind Farm
79.8 MW generation in Madison, NY · In queue since October 2024 · Proposed COD October 2029
79.8 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
The proposed Rolling Upland Wind Farm is a 79.8 MW wind energy generation project located in Madison County, New York. Developed by Rolling Upland Wind Farm LLC, the project consists of 79.8 MW of wind capacity. It is listed in the NYISO interconnection queue as entry NYISO-C24-322, with a queue entry date of October 7, 2024, and a proposed commercial operation date of October 1, 2029. The point of interconnection is the County Line-Brothertown 115kV line, and the project is interconnected with NYSEG.
The Rolling Upland Wind Farm project has been mentioned in recent industry news articles.
Generated from interconnection queue and public data sources
State
NY
County
Madison
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Rolling Upland Wind Farm LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
County Line-Brothertown 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Ross County Solar Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.