Van Buren Storage
150 MW storage in Chautauqua, NY · In queue since October 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Van Buren Storage project is a proposed 150 MW battery storage project located in Chautauqua County, New York. Developed by Origis Development LLC, the project entered the NYISO interconnection queue on October 8, 2024, under queue ID NYISO-C24-325. The proposed commercial operation date is December 1, 2028.
The project is currently listed as active in the NYISO queue. It would interconnect at the Dunkirk to Falconer 115kV Line 160. The Van Buren Storage project has been the subject of recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Origis Development LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Dunkirk to Falconer 115kV Line 160
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.