North Creek
199.5 MW hybrid in Oneida, NY · In queue since October 2024 · Proposed COD December 2027
199.5 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
North Creek is a proposed 199.5 MW hybrid solar and battery energy project located in Oneida County, New York. Developed by North Creek Solar LLC, the project consists of 199.5 MW of solar capacity. It is interconnected to the NYISO grid at the EDIC to GORDON ROAD 345kV, Line #14 point of interconnection.
The project is listed in the NYISO interconnection queue as entry NYISO-C24-327, with an original queue entry date of October 8, 2024, and a proposed commercial operation date of December 1, 2027. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
NY
County
Oneida
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
North Creek Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
EDIC to GORDON ROAD 345kV, Line #14
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about North Creek