Hell Gate Energy Storage
90 MW storage in Bronx, NY · In queue since October 2024 · Proposed COD December 2030
90 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2030
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-01
The Hell Gate Energy Storage project is a proposed 90 MW battery storage development in Bronx County, New York. The project, being developed by the NY Power Authority (NYPA), is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-331, with a queue entry date of October 9, 2024. The proposed commercial operation date is December 1, 2030.
The project consists of 90 MW of battery storage capacity. It is interconnected at the Hell Gate Bus Section 2 - 138kV. The Hell Gate Energy Storage project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Bronx
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
the NY Power Authority
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Hell Gate Bus Section 2 - 138kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hell Gate Energy Storage